Fisher Parade Seawall
Scope of works
Supply and construction of a basalt sea wall. This included rehabilitation of the existing bank, excavation of a seawall toe on the foreshore, import and place compacted suitable fill, installation of geotextile cloth, under layer rock and certified basalt boulders handpicked and graded. Construction of basalt rock steps and ramps. Project was in a public reserve and marine foreshore so works were carried out to ensure members of the public were kept safe, and could still access the walkway around the reserve. As the works were tidal, a project plan was developed to ensure works carried on throughout the tidal movement.
Client
Auckland Council
Date
December 2016
Location
Fisher Parade – Pakaranga
Budget
$620000k
LSC Division
Coatal